Deadline for Ub – Lajkovac section to be extended under reliable guarantees
As Ministry of Construction, Transport and Infrastructure announces, the interest of the country is to finish this section in a short space of time an it is obvious that current deadline, 30 June 2014, will be missed.
The Government is eager to extend the deadline for contractors, "Putevi Uzice" and "Planum", to 30 November 2014, without changes in funding, if they meet their obligations regularly, specified Secretary in the Ministry, Dejan Trifunovic.
The Government will insist on strict inspection and expert surveillance on a ten-day basis, he said.
As Ministry of Construction, Transport and Infrastructure claims, one kilometer of the road costs EUR 7 million and during last 2.5 years 12 annexes have been signed to the contract.
Most Important News
06.04.2024. | Agriculture
Preconditions for Placement of Fresh Blueberries and Dried Plums in Chinese Market Secured
16.04.2024. | News
Jovan Ciric, Leasing Director Retail MPC Properties – MPC Echo symbolizes our desire for good ideas and innovative endeavors to spread freely and bring about positive changes
16.04.2024. | News
10.04.2024. | Finance, IT, Telecommunications, Tourism, Sports, Culture
Creative Industry – What This Serbian Economy Sector Worth EUR 2 Billion Encompasses
10.04.2024. | Finance, IT, Telecommunications, Tourism, Sports, Culture
25.04.2024. | Construction, Transport
Railroad from Novi Sad to Subotica connected – Regular traffic at year’s end
25.04.2024. | Construction, Transport
16.04.2024. | News
Economy Fair in Mostar opens – 26 companies from Serbia exhibiting
16.04.2024. | News
26.04.2024. | Construction
New business quarter in the center of Belgrade – Artklasa, a place where employees love to go to work
26.04.2024. | Construction