Modernization of Constantine the Great Airport – New Light Signalization to be Installed This Year, Terminal Building and Control Tower to be Built in 2021
With the installation of the light signalization, the ALS system will be completed.
The Nis Constantine the Great Airport has the most favorable weather conditions in the region – only two to three foggy days in a year. For that reason, it has always been a good alternative to the Belgrade Nikola Tesla Airport.
The procurement of X-ray devices, scanners, metal detector gates and other equipment necessary for the control of passengers, luggage and goods for a safe transport with aircraft from the Nis Airport, has also been completed.
The period of the ban on flights, due to the epidemic, was used at the Nis Ariport for the preparation of a space where the construction of a new terminal building is to start next year.
– The works will be carried out in phases so that the airport can function normally, and the construction should be completed by 2023. The new building will be meant for the departing passengers, with commercial features and rooms necessary for the operation of airport services. The existing building will also be reconstructed and adapted to the new complex. It will be a space for the arriving passengers and the employees at the Aerodromi Srbije company. What remains is to finish the preparation of the terrain for the expansion of the platform and the taxiway – Zdravkovic says.
After the completion of these project, the Nis Airport will have 10,000 square meters of space, which will provide all the necessary comfort to the citizens who use the services of the airport. The estimate is that the construction and the equipment of the new terminal building will cost 7 to 9 million euros, and the funds will come from the budget of the Republic of Serbia.
Aerodromi Srbije signed an agreement on a long term lease for the construction of a new control tower with the Serbia and Montenegro Air Traffic Services (SMATSA) this January. The epidemic has considerably slowed down the preparation of the preliminary design, but the plan for the construction to start in 2021 is still in effect, the company says.
Most Important News
11.03.2024. | Healthcare
Are Marketing Experts Reading Our Minds? – eKapija Investigates: What Neuromarketing Is and How Much It Is Used in Serbia
11.03.2024. | Construction, Transport
Tender for Continuation of Construction of Patrijarha Pavla Blvd Stopped – Contractors Demanding Price Higher Than Estimated
11.03.2024. | Construction, Transport
11.03.2024. | Construction, IT, Telecommunications
Auction for 5G Network by End-Year, Minister Announces
11.03.2024. | Construction, IT, Telecommunications
28.03.2024. | Construction
Beginning of Construction of First “Green Dam” in Serbia Which Will Supply 500,000 People with Drinking Water
28.03.2024. | Construction
17.01.2024. | Industry, Healthcare
Ceremony of Opening of Centers of Excellence in Kragujevac Planned for Spring – Official Beginning of Operations in June
17.01.2024. | Industry, Healthcare
27.03.2024. | Industry, Transport, Finance
City to Waive Over 30 Zemun and Palilula Bus Lines to Private Transporters – Draft Public-Private Partnership for 10-Year Period Ready, Job Worth Half a Billion Euros
27.03.2024. | Industry, Transport, Finance