Final preparations for raising of columns for Zlatibor ski lift in progress
The contractor is Kraljevo-based Amiga, and the works are supervised by experts from the French company Pomagalski.
The anchors have been set and the concrete has been poured in the foundations. Once it has dried, in the next 10 to 15 days, the columns will be set up.
As the PE Gold Gondola Zlatibor announced, this counters the speculations about the equipment for the 9-km ski lift being obsolete and Pomagalski not working properly and facing bankruptcy.
– The equipment is new and properly stored. Pomagalski is involved in all activities related to the Zlatibor gondola. They understand all the problems that are the result of the delayed obtaining of permits and they are losing money together with the Municipality of Cajetina because the gondola is not yet operational, and we are being forced to apologize while not being guilty – said the director of Gold Gondola Zlatibor, Bojana Bozanic.
Most Important News
11.03.2024. | Healthcare
Are Marketing Experts Reading Our Minds? – eKapija Investigates: What Neuromarketing Is and How Much It Is Used in Serbia
11.03.2024. | Construction, Transport
Tender for Continuation of Construction of Patrijarha Pavla Blvd Stopped – Contractors Demanding Price Higher Than Estimated
11.03.2024. | Construction, Transport
11.03.2024. | Construction, IT, Telecommunications
Auction for 5G Network by End-Year, Minister Announces
11.03.2024. | Construction, IT, Telecommunications
27.03.2024. | Industry, Transport, Finance
City to Waive Over 30 Zemun and Palilula Bus Lines to Private Transporters – Draft Public-Private Partnership for 10-Year Period Ready, Job Worth Half a Billion Euros
27.03.2024. | Industry, Transport, Finance
17.01.2024. | Industry, Healthcare
Ceremony of Opening of Centers of Excellence in Kragujevac Planned for Spring – Official Beginning of Operations in June
17.01.2024. | Industry, Healthcare
27.03.2024. | Construction, Healthcare
Contractors for Construction of Tirsova 2 to Be Sought in Competitive Procedure with Negotiation – State Opens New Tender, Price Remains Same
27.03.2024. | Construction, Healthcare