Energoprojekt Niskogradnja and Colas Rail to lay down tracks on Ada Bridge – Tram traffic to open no sooner than in July 2019
The Belgrade Land Development Public Agency reached the decision to award the contract worth RSD 1.97 billion (around EUR 16.4 million) to the group of bidders consisting of Energoprojekt Niskogradnja and France’s Colas Rail.
As the document states, the completion deadline period is 420 days from the possession of the site. Ideally, then, tram traffic on the Ada Bridge will open in July 2019 if there are no complaints by any of the parties that have not been awarded the contract. If there are, however, it could postpone the construction and maybe even invalidate the tender.
The other two offers were sent by Austria’s Strabag and the group of bidders headed by the Spanish company Copisa.
Let us remind that the previous tender fell through in 2017, as the Belgrade Land Development Public Agency had deemed neither of the three bids to be acceptable.
Most Important News
06.04.2024. | Agriculture
Preconditions for Placement of Fresh Blueberries and Dried Plums in Chinese Market Secured
16.04.2024. | News
Jovan Ciric, Leasing Director Retail MPC Properties – MPC Echo symbolizes our desire for good ideas and innovative endeavors to spread freely and bring about positive changes
16.04.2024. | News
10.04.2024. | Finance, IT, Telecommunications, Tourism, Sports, Culture
Creative Industry – What This Serbian Economy Sector Worth EUR 2 Billion Encompasses
10.04.2024. | Finance, IT, Telecommunications, Tourism, Sports, Culture
24.04.2024. | Construction, Healthcare
Price of construction of Tirsova 2 increases to EUR 141.6 million – Contract awarded to consortium of 10 companies
24.04.2024. | Construction, Healthcare
16.04.2024. | News
Economy Fair in Mostar opens – 26 companies from Serbia exhibiting
16.04.2024. | News
24.04.2024. | Construction, Transport
Dates of publishing of tenders for construction of three sections of fast railroad from Belgrade to Nis known
24.04.2024. | Construction, Transport