Around 90% of Works on Velika Plana Compressor Station, Built by 1,500 Workers, Completed

Source: Tanjug Sunday, 01.08.2021. 12:30
Comments
Podeli
Illustration (Photo: SergBob/shutterstock.com)Illustration
The Velika Plana Compressor Station, the only one on the Balkan Stream gas pipeline route, is 87.4% completed, stated the director of Srbijagas, Dusan Bajatovic.

He visited the location between Velika Plana and Zabari where the compressor station is being built with the president of Serbia, Aleksandar Vucic, and said that the station operated in line with the most modern fire protection standards. He added that around 1,500 workers were active each day at the construction site.

Bajatovic said that the plan was for the gasification of eastern Serbia to start from there. He added that a plan for the gasification of Valjevo was being prepared as well and that the expropriation of the land was to start. When it comes to the gasification on the stretch from Leskovac to Vranje, Bajatovic said that the preparations were in progress and that the works on the section should start in October.


Vucic told Bajatovic that he wanted gas connections to also be established in Surcin, Bela Crkva and Kovacica.

The investor in the project is Gastrans, a joint company of Gazprom and Srbijagas, and the Velika Plana Compressor Station is being built by IDC.

Comments
Your comment
Full information is available only to commercial users-subscribers and it is necessary to log in.

Forgot your password? Click here HERE

For free test use, click HERE

Follow the news, tenders, grants, legal regulations and reports on our portal.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno, uz konsultacije sa našim ekspertima.