Machines from Russia arrive, concrete from tunnels to be removed after all – Works to be completed by October 20
– The mistake was that there were, on certain sections, not in the entire length of the road, deviations from the levels defined by the plan and the standards. The contractor for Sarani and Brdjani was Planum and all the additional works on bringing the road back in line with the plan will be charged to them – Radicevic pointed out.
He added that Sarani would be completed in eight to ten days, which means 1,500 square meters being completed a day in two shifts and during the weekends. Immediately following the completion of this tunnel, the machine will start working on Brdjani.
– We expect everything to be completed by October 20 on both tunnels, and the length of the sections being repaired is around 2.5 kilometers – Radicevic said.
The tunnels on the Ljig-Preljina section of Corridor 11 have been the center of attention in the past weeks following the allegations that they are too low for trucks to pass through, later denied by the Corridors of Serbia.
Deputy Prime Minister and Minister of Construction, Transport and Infrastructure Zorana Mihajlovic stated that the height of the tunnel was not the problem, that old machines had been used, causing the concrete road base to be done poorly, and that Planum needed to get new machines to repair the section – to remove a centimeter of the base and level the road.
On the other hand, the director of Planum, Ratomir Todorovic, said a few days ago in his interview for TV N1 that “neither are the tunnels too low, nor is the base uneven – no mistakes have been made and it’s all made up”.
Commenting on the statement by Mihajlovic that he was responsible for the poorly performed works on the tunnel, due to having deployed old machines, while new ones were being used in Russia, Todorovic answered that “only someone not versed in construction could say that”.
He also explained that the conception of the tunnels on Corridor 11 was such that new machines couldn’t even enter them. Deviations of 30 cm, as he said, are impossible, as everything in monitored and measured on a daily basis.
– It’s not like we’re making a tunnel to hand it over at one point. Instead, everything is being controlled every day – he said in his interview for N1. Planum has been operating in Serbia for 70 years and also abroad for the past 20 years. It’s one of the two Serbian companies, the other one being Energoprojekt, which raises tunnels, which is why, as Todorovic said, they get offended when someone tells them they can’t do their job, as minister Mihajlovic has done.
Most Important News
06.04.2024. | Agriculture
Preconditions for Placement of Fresh Blueberries and Dried Plums in Chinese Market Secured
16.04.2024. | News
Jovan Ciric, Leasing Director Retail MPC Properties – MPC Echo symbolizes our desire for good ideas and innovative endeavors to spread freely and bring about positive changes
16.04.2024. | News
10.04.2024. | Finance, IT, Telecommunications, Tourism, Sports, Culture
Creative Industry – What This Serbian Economy Sector Worth EUR 2 Billion Encompasses
10.04.2024. | Finance, IT, Telecommunications, Tourism, Sports, Culture
24.04.2024. | Construction, Healthcare
Price of construction of Tirsova 2 increases to EUR 141.6 million – Contract awarded to consortium of 10 companies
24.04.2024. | Construction, Healthcare
16.04.2024. | News
Economy Fair in Mostar opens – 26 companies from Serbia exhibiting
16.04.2024. | News
24.04.2024. | Construction, Transport
Dates of publishing of tenders for construction of three sections of fast railroad from Belgrade to Nis known
24.04.2024. | Construction, Transport